Progress

Updated 04-11-2026

This page is how the steps are followed: where we are, what comes next. Read next: Decisions · The 11 modules.

We are at step 3 of 7, the mockups. Step 2, the specifications, was signed off on 26-10-2026; its copy is in History.

How a step moves

The work is cut into seven steps, each producing something you can read or click. Every step gets the same four marks, always in this order:

Mark What it means Who
Written The step's documents exist Claude, from the sources and earlier decisions
Agreed in principle melux has read each document and agrees with its direction; open questions are answered melux
Checked by reviewers Two agents, Claude and Codex, each look for what is wrong or missing, on their own; every finding is numbered and answered in the step's reviews, in the columns set out in history D50 the agents; melux decides what the findings change
Signed off The step is final and dated; its copy is kept in history melux, after colleagues' comments

Nothing is drawn or built before a step is signed off.

Every question asked along the way, answered or not, is kept in the questions and answers, by round D50. An open question is written with who asked it and when, its options, the one recommended and why, and what happens if no one answers.

How a module page is written

Step 2 has one page per module, each in the same template D49, at most 450 words:

Part What it holds
Definition and examples What the module is in two or three sentences, with real examples from Burundi or Rwanda
Functions Numbered and grouped; the continuity table says which function of v7 or of the prototype each one takes over
Rules What always holds, written as a rule a tester can check
Decisions needed Open questions, in the form above, numbered in the ledger
Related documents What the page was written from, at which commit, and what was not seen

A function of v7 or of the prototype found on the way is added to the continuity table first, with a new F-number, then to its module.

The seven steps

Step
WrittenAgreed in principleChecked by reviewersSigned off
  1. 1
  2. 2
  3. 3
    second pass written · 04-11first pass · 04-11
  4. 4
    4 · Detailed specificationsContract, engine rules, one sheet per tax, failure policies
  5. 5
    5 · Detailed mockupsEvery state: empty, error, customs down, shadow
  6. 6
    6 · Build phasesOne branch and one pull request per phase
  7. 7
    7 · The toolBuilt phase by phase
  8. 7.1
    ASYCUDA provider and the page, Burundi live
  9. 7.2
    Engine and ingestion; pilot 1, Burundi against OBR
  10. 7.3
    Administration: versions, differences, publishing
  11. 7.4
    Embedding and the eRegulations v7 change
  12. 7.5
    Pilot 2, Rwanda

Timeline

Date What happened
28-09-2026 The work asked for: turn the Burundi prototype into a calculator any portal can embed
29-09-2026 Step 1 written, agreed in principle, checked by reviewers
30-09-2026 Step 1 signed off. Step 2's eleven modules written, agreed in principle and checked; the contract and the states of the page added
30-09 to 01-10-2026 First colleague comments: Mehdi Benmoumen, Frank Grozel, Julien Bornon
15-10-2026 The way of working brought back from eRegulations-Next, which had taken it from here: the breadcrumb, larger text, the questions ledger, the continuity table, French pages (D49 to D51)
15-10-2026 The specifications brought level with v7's tariff page up to release 7.6.49; three new questions, ?37 to ?39
26-10-2026 KRA's tax calculator read; two questions, ?40 and ?41; ?37 to ?41 answered (D52 to D56)
26-10-2026 Step 2 signed off; its fourteen pages kept as they were in History
26-10-2026 Step 3's first pass written: v7's tariff page reproduced, with five differences
29-10-2026 The Kenya Duty Estimator read; it becomes the second pass's reference and D56's case D57
04-11-2026 Step 3's first pass agreed in principle
04-11-2026 Step 3's second pass written and checked in part: the design, the clickable mockups, 82 rows replayed at 1 280 and 375 pixels, 28 of them walked by hand at 1 280, the print dialog not seen
Next melux's agreement on the second pass

Waiting and stuck

Waiting on melux

Agreeing the second pass of the mockups, written on 04-11-2026 and checked in part (28 of its 82 rows by hand at 1 280 pixels, all replayed at both widths, the print dialog not seen; the first pass was agreed in principle on 04-11-2026). Administration then gets a third pass before step 3 is signed off D59.

Stuck

OBR's test service, silent since 04-09-2026. Waiting on OBR's IT department.

Blocks only new cases from the test host; pilot 1 uses production instead D24.

Drafted with Claude for melux · UNCTAD · working material, hidden from search enginesUpdated · 04-11-2026